Over the past several months, Rambler’s construction team has been busy!
Today, we’ll be providing updates on:
Units
Ownership and the general contractor have begun quality control reviews of the units. During this process, we test all appliances, light fixtures, and review the quality of finishes to ensure an outstanding product on move-in.
We’ve currently reviewed 50% of the units. Appliances, HVAC, and water are all working properly.
Inside the property, unit finishes including lighting, white quartz countertops, matte black hardware and stainless steel appliances are complete in the North Building and nearly complete in the South Building.
Bathroom shower tile and fixtures are in place in both buildings.
Corridors are also receiving final paint and carpet flooring and elevator lobbies will soon be completed.
Amenities
Wood trim and hardwood flooring are being installed at the monumental stair in the lobby and Daydreamer cafe.
Mailboxes were installed last week and bathroom tile has just started. Our decorative light fixtures have been installed in the gameday lounge and will soon be installed throughout.
The contractor has just finished installing the stone coping and waterline tile for the pool and the pool decking is being prepped for concrete. We are currently running gas to the outdoor grills and fire pits.
Exterior
Brick and siding installation are 90% complete and exterior painting will be finished in April. The contractor is working on finishing Finely Street and will move to installing all the sidewalks around the perimeter of the buildings.
Unit Walkthroughs
Check out the progress on our units by watching our walkthroughs below!
The Hancock
View this post on Instagram
The Milledge
View this post on Instagram
The Finley
View this post on Instagram
The Prince
View this post on Instagram
The Jackson
View this post on Instagram
The Broad
View this post on Instagram
The Sanford
View this post on Instagram
Want to see more unit walkthroughs? Follow us on Instagram for regular updates.
We are on track for an on-time delivery and excited to continue to show you updates as we finish out these spaces. And remember, we’re so confident that Rambler will deliver on time, we guarantee it.
We hope you enjoyed this construction update, and we can’t wait to welcome all of our residents in August. Stay tuned for more updates! If you have any questions, contact our leasing staff – we are happy to help you in your search for housing.